Financial Situation of the STABEX
funded projects (Kina '000) |
|
|
|
|
|
Situation
as of 31.12.2003 |
|
|
|
|
|
B. |
FMO 90-94 for Bougainville |
|
|
|
|
|
No |
Project Title |
Amount Allocated |
Amount Committed |
Amount Paid |
Status |
|
B.1. |
Agric. & Econ. Infrastr. |
|
|
03A |
Bougainville Agricultural Feeder roads |
3,500.00 |
3,500.00 |
1,500.00 |
Ongoing |
|
06A |
Arawa Town Market |
500.00 |
500.00 |
- |
Ongoing |
|
|
Sub-total |
4,000.00 |
4,000.00 |
1,500.00 |
|
B.2. |
Agriculture Rehab. |
|
|
02A |
Distribution of manual rice huskers in Bougainville |
70.00 |
70.00 |
70.00 |
Completed |
|
02B |
Co-financing of a Bougainville Cocoa Sector Rehab. Programme, UNDP |
3,200.00 |
3,200.00 |
2,235.22 |
Ongoing |
|
02C |
Coconut
Genetic Improvement Bougainville Attols |
215.00 |
215.00 |
195.00 |
Ongoing |
|
02E |
Togarau
Potato Seed Production & Marketing Study Project |
10.00 |
10.00 |
5.00 |
Completed |
|
02F |
Atoll Agricultural Research and Development Programme |
495.87 |
495.87 |
169.90 |
Ongoing |
|
04A |
Appraisal, Design Costing of Various Credit Schemes |
107.50 |
107.50 |
107.50 |
Completed |
|
04B |
Bougainville Rural Agriculture Credit Scheme |
2,000.00 |
- |
- |
Awaiting Start-up |
|
04C |
Bougainville Women's Micro Credit Scheme Workshop |
25.00 |
25.00 |
25.00 |
Completed |
|
04D |
Bougainville Women's Micro Credit Scheme |
600.00 |
- |
- |
Awaiting Start-up |
|
|
Sub-total |
6,723.38 |
4,123.38 |
2,807.63 |
|
B.3. |
Training Programme |
|
|
05A |
Mabiri Vocational and Rehabilitation School |
74.00 |
74.00 |
74.00 |
Completed. Yet to be closed |
|
05B |
Training for DPI staff |
105.00 |
105.00 |
102.57 |
Ongoing |
|
05C |
St Gregory Vocational school |
758.10 |
758.10 |
497.91 |
Ongoing |
|
05D |
Tunuru Vocational Training Center |
731.85 |
731.85 |
485.43 |
Ongoing |
|
05E |
Buin vocational training center |
758.60 |
758.60 |
300.00 |
Ongoing |
|
05F |
Tinpuz Vocational Training Center |
870.00 |
870.00 |
323.49 |
Ongoing |
|
|
Sub-total |
3,297.55 |
3,297.55 |
1,783.40 |
|
B.4. |
Supervision |
|
|
01A |
BPIU/Operational Expenditure |
2,068.76 |
2,068.76 |
1,413.96 |
Ongoing |
|
01B |
BPIU/Coordinator |
414.70 |
414.70 |
365.00 |
Completed |
|
01C |
BPIU/infrastructure coordinator |
457.10 |
457.10 |
235.00 |
Completed |
|
|
Sub-total |
2,940.56 |
2,940.56 |
2,013.96 |
|
|
|
|
|
Total FMO 90-94 for Bougainville |
16,961.48 |
14,361.48 |
8,104.99 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|