Financial Situation of the STABEX funded projects (Kina '000)
Situation as of 31.12.2003
A. FMO 92/93/94
No Project Title Amount Allocated Amount Committed Amount Paid Status
A.1. Debt relief
3.1 Price support to debt relief/Cocoa         922.21         922.21         922.21  Completed 
3.2 Price support to debt relief/ Copra      1,765.40      1,765.40      1,765.40  Completed 
3.3 Price support to debt relief/ coffee (FMO 92/93)    14,772.90    14,772.90    14,772.90  Completed 
Sub-total   17,460.51   17,460.51   17,460.51
A.2. Bougainville
1.2 North solomon restoration programme         110.00         110.00         110.00  Completed. Yet to be closed 
1.6A Bougainville women micro-credit scheme         100.00         100.00         100.00  Completed 
1.6C Agricultural feeder road improvement works/Buka Island      1,750.00      1,750.00      1,750.00  Completed. Yet to be closed 
1.6D Agricultural coordinator Bougainville restoration         425.00         425.00         425.00  Completed. Yet to be closed 
1.6E Port infrastructure in Bougainville      1,440.00      1,440.00      1,108.61  Ongoing 
1.6F Bougainville cocoa and coconuts census           44.00           44.00           44.00  Completed. Yet to be closed 
1.6G RRA for Bougainville rehabilitation programme           85.00           85.00           72.02  Completed 
1.6H Post-evaluation of Bougainville micro credit scheme           45.00           45.00           30.22  Completed 
Sub-total     3,999.00     3,999.00     3,639.85
A.3. Cocoa & Coconut
1.1 Research and extension at CCRI      4,330.00      4,330.00      4,330.00  Completed. Yet to be closed 
1.3 Rehabilitation of trading facilities/CMB         705.00         705.00         705.00  Completed 
1.4 Rehabilitation of cocoa Board         815.00         815.00         815.00  Completed. Yet to be closed 
1.5 Coconut beetle control programme, CCRI      2,568.00      2,568.00      2,568.00  Completed. Yet to be closed 
1.6B Repairs and refurbishment of Rabaul CMB shed/CCRI         797.00         797.00         445.00  Completed. Yet to be closed 
1.7 New office block Tavilo, CCRI, Project      2,312.39      2,312.39      2,312.39  Completed. Yet to be closed 
1.8 Cocoa market research, promotion, Price, Monitoring and export training         300.00         300.00         172.46  Ongoing 
1.9 Rehabilitation activities at CCRI         370.00         370.00         370.00  Completed. Yet to be closed 
1.10 Redevelopment of cocoa sites with planting materials, CCRI         150.00         150.00           50.00  Completed  
Sub-total   12,347.39   12,347.39   11,767.85
A.4. Coffee
2.1 Research activities CIC         690.00         690.00         690.00  Completed. Yet to be closed 
2.2 Extension activities (coffee), CIC      1,070.00      1,070.00      1,070.00  Ongoing 
2.3 Coffee pulpers          262.00         262.00         262.00  Completed. Yet to be closed 
2.4 Coffee promotion stage I         180.00         180.00         180.00  Completed. Yet to be closed 
2.5 Coffee chemical taste control stage I         540.00         540.00         540.00  Completed. Yet to be closed 
2.5B Coffee chemical taste control stage II      1,076.00      1,076.00      1,076.00  Completed. Yet to be closed 
2.6 Coffee Grower owned , marketing groups      2,600.00                -                  -    Awaiting Start-up 
2.7 Coffee Workshop           70.00           70.00           70.00  Completed  
2.8 CIC Corporate Restructure Project         234.00         234.00         234.00  Completed 
2.9 Western Highlands Sub-station Development (CIC)         692.20         692.00         275.00  Ongoing 
2.10 CRI/CIC Administrative and Infrasrtucture Support Project          667.30         667.30         396.04  Ongoing 
2.11 CRI integrated Management of Green Scale         242.65         242.65         120.00  Ongoing 
2.12 Capacity building for the Mass Propagation center         314.00         314.00         100.00  Ongoing 
2.13 CIC treatment of coffee processing wastes         150.00                -                  -    Awaiting Start-up 
Sub-total     8,788.15     6,037.95     5,013.04
No Project Title Amount Allocated Amount Committed Amount Paid Status
A.5. Oil Palm
3.4A  Redevelopment of Kavugara oil palm blocks, OPIC      2,500.00      2,500.00      2,500.00  Completed. Yet to be closed 
3.4B Assistance to Biala Growers         500.00         500.00         500.00  Completed 
4.1 Extension activities at OPIC      4,004.60      4,004.60      3,941.20  Completed. Yet to be closed 
4.2 Ganoderma research project, PRA      1,892.43      1,892.43      1,892.43  Completed 
4.2B Ganoderma Research Project Second Phase (OPRA)         992.00         992.00         400.00  Ongoing 
4.4 Management staff training for oil palm industry, PACRIM      1,800.00      1,800.00      1,200.00  Completed. Yet to be closed 
4.5 Research in the biological control of sexava, OPRA      1,105.00      1,105.00      1,105.00  Completed 
4.6 In country training in applied statistics at PNG OPRA         223.64         223.64         223.64  Completed 
4.7 Mainten. of agric. roads for smallholders oil palm producers         229.00         229.00         229.00  Completed 
4.18 Insect pollination of oil palm, OPRA         500.00         500.00         489.65  Completed 
4.18 B Insect pollination of oil palm, OPRA second phase         556.50         556.50         220.00  Ongoing 
4.22 OPRA efficiency of Nitrogen Fertiliser inputs project         680.31         680.31         252.52  Ongoing 
Sub-total   14,983.48   14,983.48   12,953.44
A.6. Agriculture Rehab.
4.8 Extension of NARI      2,000.00      2,000.00      2,000.00  Completed  
4.9 Rehabilitation of Low lands LAES         526.50         526.50         526.50  Completed 
4.11 statistics compilation for Stabex eligibility             5.00             5.00             5.00  Completed 
4.12A Launakalana  feasibility study         131.35         131.35         131.35  Completed 
4.12B Launakalana preparation phase         350.00         350.00         350.00  Completed 
4.12C Launakalana Cashew nut project      3,500.00      3,500.00      1,045.50  Ongoing 
4.13 Sheep breeding programme, DAL         227.00         227.00         204.74  Ongoing 
4.19 PNG food and nutrition conference           24.99           24.99           24.99  Completed 
4.21 Appraisal of FPDC STABEX submission           40.00           40.00           40.00  Completed 
4.26 Rural Industries Council (Information unit)         306.30         306.30           80.00  Ongoing 
4.27 Improved Food security and Farmers income (NARI)         297.05         297.05         110.40  Ongoing 
4.28 Abbatoir and cool room facilities, (Vudal University)      1,200.00      1,200.00         765.72  Ongoing 
PNGRIS upgrading, (DAL)         750.00                -                  -    Awaiting Start-up 
4.31 NARI Commercialisation of alternative cash crops (NARI Kerevat)         344.04         137.61                -    Ongoing 
Feasibility study for central province, grain growing project          260.55                -                  -    Awaiting Start-up 
Sub-total     9,962.79     8,745.80     5,284.21
A.7. Forestry - Fisheries
4.3 PNGFA Log monitoring (+ rider)    12,000.00    12,000.00    11,000.00  Ongoing 
4.10 IREP mainland      1,360.83      1,360.83      1,290.00  Completed. Yet to be closed 
4.16 IREP island region      2,403.79      2,403.79      2,320.17  Completed. Yet to be closed 
4.20 Fully fledged Audit of IREP           22.00           22.00           22.00  Completed 
4.24 HACCP programme for fishing industry         282.46         282.46         140.00  Completed. Yet to be closed 
4.29 Remote sensing and land use planning (UPNG)         600.00         600.00         300.00  Ongoing 
Sub-total   16,669.08   16,669.08   15,072.17
A.8. Other Sectors
4.15 Audit of 8 Stabex projects           30.00           30.00           30.00  Completed 
4.17 Audit of 15 Stabex projects           38.00           38.00           38.00  Completed 
4.23 NCDC Mini markets      1,000.00         234.00         115.00  Ongoing 
4.25 Financial Monitoring of STABEX funds         180.00         180.00           90.00  Ongoing 
4.30 Audit of STABEX Accounts         100.00         100.00           84.35  Ongoing 
Sub-total     1,348.00        582.00        273.00
Total FMO 92/93/94    85,558.39    80,825.21    71,464.07